2013-04-25 - 6610 - Service Request - Production order not referencing to BOM #ProductionBreakFix #ProductionOrders #US

2013-04-25 - 6610 - Service Request - Production order not referencing to BOM

Problem Summary


Production order not referencing to BOM

Admin Info


Purpose
Production order not referencing to BOM
Requested by
Babu Lankipalli, Doug Snyder
Issue Date
04-25-2013
Resolved by
Adithya
Resolved Date
04-25-2013
Document Status
Complete

Detailed Problem Description

(Include Screen Shots if required )

Production order 1000536874 not referencing to BOM "No material components are allocated to the order" is the error.

Solution Analysis and Recommendations

(Include Screen Shots if required)

It is observed that Production Order 1000536874 is s created before the master data explosion date.

Resolution


Follow the below steps:
1. As 1st operation is confirmed Cancel the Confirmation of first operation
2. Read PP Master Data.
which shall re explode the BOM and components will allocated to the order.

Release Information


Provide link here to Release Notes if Technical Objects were changed